After the indoor unit is suspended, check the pipe / wire connections inside the ceiling and choose a place for installation, determining the direction of the pipe.
• If the ceiling is already installed, route the refrigerant pipe, the drain pipe, the internal connection wires, the remote control wire, etc. to where the tubes and wires are, before suspending the main unit.
• Check the size of the indoor unit and match its size with the size of the opening in the ceiling and organize the positions, using the manufacturer's installation pattern.
(Secure the frame to the lower side of the indoor unit with the four M5 x 16 l screws.)