Once the preparation for starting the central conditioner has been carried out, the unit is ready to go into operation.

 The start must always be given by qualified and trained people.


Verifications:

• Check the direction of rotation of the fans (indicated by an arrow on the fan's own volutes).

• Check that the electrical current of the evaporator motor is not greater than the rated value.

• Check the evaporator flow or fan speed values are within the specified in the installation project.

• If the compressor presents a high noise and there is no pressure differential between discharge and suction, check the sequence of the power supply phases.

• Check that the siphons and drains are working properly.

• Make sure that there is no leakage in the refrigerant circuit.

• Adjust the gas load if necessary, according to the manufacturer's guidelines.